The Unsolicited Proposal Dilemma: How Governments Can Protect the Public Interest
Unsolicited proposals can unlock investment, but only with the right legal safeguards in place. Without them, governments risk being locked into decades of hidden costs.
Many African governments have large infrastructure needs – roads, power plants, water systems – but lack the public budgets to build them. With state budgets stretched by salaries, debt servicing, and social spending, it creates a gap for private companies to step into with offers to design, finance, build, or operate these important projects.
These unsolicited proposals are usually structured as public-private partnerships (PPPs). They are attractive to governments because when private partners raise most of the upfront capital, treasuries avoid taking on upfront debts. Payments can be spread over decades allowing governments to plan beyond budget cycles and commit to projects they could not otherwise afford. The returns can be substantial. Good infrastructure attracts further investment, creates jobs, and delivers the foundations of sustained economic growth.
Most PPPs begin with the government identifying a project and inviting bids. But with unsolicited proposals, the company identifies the project and often arrives with financing arranged. For governments, this can open doors to international investors they would otherwise struggle to reach. Yet the companies also often write the assumptions the deal rests on, arriving with their own demand forecasts, feasibility studies and financial models.
Independent scrutiny is therefore necessary to avoid terms that primarily benefit the private company. Managing the risks requires clear legislation, transparent decision-making, and officials equipped to apply the necessary safeguards. Without these practices, the consequences can be significant.
The Cost of Convenience
In 1994, Tanzania faced an energy crisis. The Government was negotiating a natural gas project when a Malaysian company, Mechmar Corporation, arrived with an unsolicited proposal to build an emergency power plant through a joint venture with a local partner, according to the Africa Research Institute.
By the time the agreement was signed in 1995, the crisis had ended. Yet the plant did not connect to the national grid for almost seven years. What followed was two decades of costly legal disputes. By relying on the company's cost data, the Government had ceded significant ground before negotiations began.
Building a Legal Framework
Developing countries can learn lessons from established PPP markets such as Australia, Canada, and South Korea which run projects through dedicated PPP bodies, compare proposals against the cost of delivering them publicly, and publish value-for-money assessments. Meanwhile, the U.K. stopped using its Private Finance Initiative for new projects in 2018 after the National Audit Office found that private finance often cost more than government borrowing. The lesson here is that PPPs can deliver value, but governments must treat them as a financing tool to be tested and implemented with the right safeguards in place.
The first of these safeguards is a dedicated body to evaluate every proposal. Drawing on precedent from the United Nations Commission on International Trade Law (UNCITRAL), the Chandler Institute of Justice (CIJ) has developed a model PPP law for the Great Lakes region. It recommends a PPP Unit within the Ministry of Finance, with a mandate to train and resource its staff, so that officials are equipped to challenge a proposal's assumptions.
Evaluating Unsolicited Proposals
The Great Lakes region is already legislating to this effect. Kenya's Public Private Partnerships Act 2021 requires the contracting authority to publish the feasibility studies and project documentation of all "privately initiated proposals". Disclosure follows a determination by Kenya's Public-Private Partnership Committee on how the proposal will be procured, giving rival bidders and the public a chance to test its assumptions before it proceeds.
Another legal protection is ensuring competitive procurement is the default, with any exceptions narrowly defined, independently reviewed and transparently justified. Following this, the proposer can be offered a capped bid preference of around 10%, or reimbursement of its development costs if another bidder wins. This is the South Korean bonus system.
Other approaches include the Swiss challenge, under which third parties bid and the proposer may match, and best-and-final-offer, under which the proposer is guaranteed a place in the final round of bidding. A further set of safeguards, below, highlights good practice at each stage of the PPP process.
Closing the Gap
When Tanzania agreed to the power plant deal in 1995, a government facing an unsolicited proposal had few legal protections. Today, these legal safeguards are within reach of any government that chooses to legislate them. CIJ has worked with the Forum of Parliaments of the Member States of the International Conference on the Great Lakes Region to develop a model PPP law that makes that process more effective.
Without CIJ's timely financial and technical support, delays were inevitable. Now, we have a robust, clear set of regulations that bring consistency to our legal framework, making our work that much more efficient.
In Zambia, this is already happening. CIJ supported the country's PPP Office in developing the regulations the Public-Private Partnership Act No. 18 of 2023 needed before officials could use it. A two-week workshop followed by consultation with government and industry, produced the PPP General Regulations and PPP Fund Regulations. Once signed into law, this gave officials the rules they needed to run a tender or evaluate a proposal.
Zambia's experience shows that a model law, legislation, or regulations are not enough on their own. Each sector has its own risks, revenue models, and regulators. A toll road depends on traffic forecasts, a power plant on purchase agreements with state utilities, and water projects on the affordability of tariffs. Sector-specific guidelines translate general rules into the tests, templates, and risk allocations officials need for each type of project. Building on the regulations, CIJ also supported Zambia's PPP Office in developing guidelines for the transport sector, giving officials practical tools to assess road and other transport projects.
Legislators must adapt model laws and regulations to their own systems and markets. While a copy-and-paste law risks becoming another set of rules on paper, a law shaped to the reality on the ground is most likely to be effective in practice. Building tailored laws, regulations, guidelines and safeguards enables African governments to attract the private investment they need to deliver their infrastructure goals on terms that serve their citizens first.